Costain - 3 Shires Batched PFI, Leicester LDU, Leicester

| Brickwork LPSM |
£250,000.00 |
| Scaffold |
£80,000.00 |
- Estimated £ 400,000.00 + (Brickwork & Scaffold) – Not yet
complete
- Labour, Plant, Sundry Materials & Scaffold
- Estimated 20 Weeks
- Strict build programme
- Difficult access & careful consideration of sequencing to allow
construction of the Pod & Courtyard areas to be completed.
- Single storey
- Complicated build – squint angles .etc